Electrical · Free · Instant results

Cable Size Calculator

Calculate Smarter. Work Faster.

Free cable size calculator for single & three phase — enter load in kW, HP or amps and cable length to get cable size (mm²), current-carrying capacity check, voltage drop % and MCB rating for copper or aluminium.

Load & Cable Run Details

Enter your load, supply, and cable run details to get a recommended cable size.

System i Single Phase uses line-to-neutral voltage across 2 wires; Three Phase uses line-to-line voltage across 3 (or 4, with neutral) wires — this changes both the current formula and the default supply voltage preset below.
Common Voltages i Includes common voltage presets used in India, the UK & Europe, North America, the Middle East, Australia and South Africa — or enter any custom voltage above. This calculator sizes cables using the metric conductor cross-sectional-area (mm²) convention commonly used in these regions; the USA and Canada size cables in AWG/kcmil under the NEC/CEC instead, which this calculator does not cover.
Conductor Material i Aluminium has lower conductivity than copper, so it needs a larger cross-section for the same current — each material uses its own reference-capacity and resistance table here. Aluminium 1.5 sq.mm is not included in this preliminary reference table.
I = (kW × 1000) ÷ (V × PF)  [1-phase, V = line-to-neutral] I = (kW × 1000) ÷ (√3 × V × PF)  [3-phase, V = line-to-line] kW to HP = kW × 1.341 Vd = 2 × I × L × (Rₜ cosφ + X sinφ) ÷ 1000  [1-phase] Vd = √3 × I × L × (Rₜ cosφ + X sinφ) ÷ 1000  [3-phase] Rₜ = R₂₀ × [1 + α(T − 20)] Capacity check: Ib ≤ In ≤ Iref × Cf

Voltage drop uses conductor resistance corrected to the selected conductor temperature plus a typical multicore LV cable reactance of 0.08 Ω/km (R·cosφ + X·sinφ). Single-core cables laid apart, very large sizes and harmonic-rich loads can have a higher effective impedance — confirm with the manufacturer’s mV/A/m data.

Preliminary Cable Size — Screening Result
— sq.mm

Enter your details and hit calculate

Load Current — A
Sizing Current — A
Preliminary Reference Capacity i This is a conservative illustrative reference value for preliminary screening only — it is not a code ampacity table and must not be treated as the allowable current for a specific installation. The planning allowance (if enabled) is included in the design current used for both the reference-capacity and voltage-drop checks below. — A
Cable Length — m
Estimated Voltage Drop (3% screening target)
—%
— Reference-capacity check
— Voltage-drop screening check
Indicative Protection Rating — Screening Only i Simplified preliminary rating only, chosen so it sits at or above the planning sizing current (Ib) and at or below this cable's reference capacity (Ib ≤ In ≤ reference capacity). This preliminary rating is based on the calculated planning current — it is not a final MCB/MCCB/RCBO/fuse selection; final selection must still verify the actual derated cable capacity, fault level, trip characteristics and coordination requirements.
— A
Neutral (default) i This is the simplified same-as-active default only — it does not check load balance or harmonic content; see the Neutral Conductor Sizing guidance below for when a different size may apply. — sq.mm
Earth/CPC (rule of thumb) i Uses a simplified rule of thumb (same as active up to 16 sq.mm, held at 16 sq.mm from 16–35 sq.mm, then half the active size above 35 sq.mm, rounded up to the next standard size) — it is not the adiabatic, fault-current-based calculation required for a final design; use the dedicated Earthing Conductor Size Calculator for that. — sq.mm
Cable Size Comparison — Reference Capacity & Voltage Drop

Calculate to compare ampacity and voltage drop across nearby cable sizes.

Next step: apply installation deratingAir / conduit / tray / buried, 70°C PVC or 90°C XLPE, ambient, grouping, thermal insulation, harmonics — in the Current Carrying Capacity Calculator. →
Did this solve your problem?

Created by Umasankar Maity — B.Tech in Electrical Engineering, with 11+ years of industrial maintenance experience.

Reviewed by the ElectroMechCalc editorial team.

Last reviewed: October 2026  |  Reference framework: IEC 60364-5-52, BS 7671, IS 7098 / IS 3961, AS/NZS 3008.1 (concepts only — values are simplified screening figures)

How it works

How to Calculate Cable Size — Step by Step

Quick answer: To calculate cable size, find the load current from kW, voltage and power factor, pick the smallest cable (mm²) whose current-carrying capacity is at least that current after derating, then check voltage drop over the cable length and step up a size if the drop is too high.

  1. Find the load current (Ib). 1-phase: I = (kW × 1000) ÷ (V × PF) 3-phase: I = (kW × 1000) ÷ (√3 × V × PF) For motors: kW = (HP × 0.746) ÷ efficiency.
  2. Add a planning margin (optional). This calculator can add +20% for spare capacity. It is not a code demand or derating factor.
  3. Choose a base size from current-carrying capacity. Pick the smallest mm² size whose capacity, multiplied by the total derating factor, is at least the design current — separately for copper or aluminium.
  4. Apply derating. Correct the tabulated capacity for ambient temperature, grouping and installation method — see derating. The calculator applies the single total factor you enter; the final design must use the factors from your governing table.
  5. Check voltage drop. 1-phase: Vd = 2 × I × L × (Rₜ cosφ + X sinφ) ÷ 1000 3-phase: Vd = √3 × I × L × (Rₜ cosφ + X sinφ) ÷ 1000 Rₜ is the conductor resistance at operating temperature and X the cable reactance (Ω/km). If Vd% exceeds the chosen limit, step up one size and re-check.
  6. Take the larger of the two. The final screening size is whichever is larger: the size set by current-carrying capacity or the size set by voltage drop. Short, heavily loaded runs are usually capacity-governed; long runs are usually voltage-drop-governed.
  7. Select protection, neutral and earth. Protective device: Ib ≤ In ≤ cable capacity. Neutral = phase size by default. Earth/CPC by rule of thumb (verify with an adiabatic check).

Worked Example: 20 kW, 3-Phase, 415 V, 60 m, Copper

  1. Load current = (20 × 1000) ÷ (1.732 × 415 × 0.85) ≈ 32.7 A.
  2. With +20% planning margin → sizing current ≈ 39.3 A.
  3. Smallest size with screening capacity ≥ 39.3 A → 10 mm² (40 A).
  4. Resistance at 70°C = 1.83 × [1 + 0.00393 × (70 − 20)] ≈ 2.19 Ω/km; with cosφ 0.85 and X 0.08 Ω/km, R cosφ + X sinφ ≈ 1.86 + 0.04 = 1.90 Ω/km.
  5. Voltage drop at 60 m = √3 × 39.3 × 60 × 1.90 ÷ 1000 ≈ 7.8 V ≈ 1.9% → passes 3%. The size is capacity-governed here.
  6. Result: 10 mm² copper, indicative protective device 40 A (39.3 ≤ 40 ≤ 40).

Screening result only — confirm with the applicable current-rating table for your installation method and derating.

Why Cable Size Matters

  • Heat: current through conductor resistance creates I²R heat. An undersized cable overheats, ages its insulation and can cause a fire.
  • Voltage drop: long runs lose voltage in the cable. Motors and equipment can overheat, underperform or trip on undervoltage.
  • Cost: oversizing adds material and installation cost — but a larger size may be chosen deliberately for voltage drop, derating or future load.
Guide

How to Use This Cable Size Calculator

  1. Select the system: single phase (e.g. 230 V) or three phase (e.g. 415 V / 400 V).
  2. Enter the load: in kW, HP (motor, with efficiency) or directly in amps.
  3. Enter power factor: use the nameplate value. Heaters ≈ 1.0; motors typically 0.8–0.9.
  4. Enter supply voltage and one-way cable length in metres, and choose copper or aluminium.
  5. Click Calculate Cable Size to get cable size (mm²), load current, voltage drop %, indicative MCB/MCCB rating, neutral and earth size, plus a comparison with nearby sizes.
Reference

Cable Size Chart (mm²) — Copper & Aluminium Screening Values

These are the simplified values this calculator uses. They are not installation ampacity — actual current-carrying capacity depends on installation method, insulation and derating.

Size (mm²) Copper (A) Aluminium (A) Cu R (Ω/km) Al R (Ω/km)
1.510—12.1—
2.516107.4112.1
425164.617.41
632253.085.09
1040321.833.08
1663401.151.91
2580630.7271.2
35100800.5240.868
501251000.3870.641
701601250.2680.443
952001600.1930.32
1202502000.1530.253
1503152500.1240.206
1853553150.09910.164
2404003550.07540.125
3005004000.06010.1
4006305000.0470.0778

Resistance values are illustrative ~20°C reference figures; the calculator corrects them to the selected conductor temperature and adds cable reactance for the voltage-drop estimate. Aluminium 1.5 mm² is not included.

Important: final cable selection must use the applicable current-rating table (e.g. BS 7671 Appendix 4, IEC 60364-5-52, IS 3961, AS/NZS 3008.1) and the cable manufacturer's data.

Ampacity

Current-Carrying Capacity & Derating Factors

Current-carrying capacity (ampacity) is the maximum continuous current a cable can carry without exceeding its insulation temperature limit. Tabulated values assume a reference condition — typically 30°C air and a single circuit. Real installations need correction:

  • Ambient temperature (Ca): hotter air → lower capacity.
  • Grouping (Cg): several loaded circuits together heat each other.
  • Thermal insulation (Ci): cables in insulated walls lose heat slowly.
  • Buried cables: soil thermal resistivity and depth also apply.
Required tabulated capacity: It ≥ In ÷ (Ca × Cg × Ci)

This size calculator applies one total correction factor that you enter — the product of the factors above. Our current carrying capacity calculator works that factor out for you — it takes installation method (air, conduit, tray or buried), PVC 70°C / XLPE 90°C insulation, ambient temperature, grouping, thermal insulation, harmonic neutral loading and parallel runs, and returns the derated ampacity. Also read Cable Derating Tips for corrected capacity.

Illustrative ambient-temperature factors — not a complete IEC/IS table.

Ambient Temp PVC (70°C) XLPE (90°C)
30°C (reference)1.001.00
35°C0.940.96
40°C0.870.91
45°C0.790.87
50°C0.710.82

XLPE derates less than PVC because it runs at a higher conductor temperature. Always multiply ambient and grouping factors together.

Voltage drop

Voltage Drop Check in Cable Sizing

  • Formula: Vd% = Vd ÷ V × 100, with Vd = k × I × L × (Rₜ cosφ + X sinφ) ÷ 1000, where k = 2 for single-phase and √3 for three-phase.
  • L = one-way length (m), R = conductor resistance (Ω/km), I = design current (A).
  • Screening target: selectable, 3% by default. Codes set their own limits — e.g. IEC 60364-5-52 and BS 7671 guidance cite 3% for lighting and 5% for other uses on a public LV supply (6% and 8% from a private supply), and NEC informational notes suggest about 3% branch / 5% total.
  • Temperature and reactance: resistance is corrected from 20°C to the selected conductor temperature (α = 0.00393/°C copper, 0.00403/°C aluminium), and a typical multicore reactance of 0.08 Ω/km is added. Reactance matters most on large sizes at low power factor; single-core cables laid apart have higher reactance.
  • Motor starting: the check is steady-state. A motor’s starting current can briefly cause a much larger drop — check it separately for large DOL motors.
  • For an R·cosφ + X·sinφ calculation, use the Voltage Drop Calculator.
Standards

Cable Sizing Standards by Region (IS, BS 7671, IEC, AS/NZS, NEC)

The calculator works with any LV supply up to 1000 V and outputs metric mm² sizes. Each region uses its own current-rating tables:

RegionTypical StandardsTypical LV SupplySize Units
IndiaIS 732 (wiring), IS 3961 (ratings), IS 7098 / IS 1554 (cable product)230 V / 415 Vmm²
UKBS 7671 (18th Edition), Appendix 4 tables230 V / 400 Vmm²
Europe & IEC countriesIEC 60364-5-52230 V / 400 Vmm²
Australia / NZAS/NZS 3008.1, AS/NZS 3000230 V / 400 Vmm²
Middle East, South AfricaMostly IEC / BS-based national codes220–240 V / 380–415 Vmm²
USA / CanadaNEC (NFPA 70) Table 310.16, CEC (CSA C22.1)120/240 V, 208/480 VAWG / kcmil — not covered

This calculator does not reproduce any standard's tables. For AWG sizing, use an NEC-based wire size tool.

Cable types

Cable Types: PVC 70°C, XLPE 90°C, Armoured (SWA) & Flexible

The same mm² size gets a different current rating depending on insulation and construction. Higher allowed conductor temperature = higher rating.

Cable TypeMax Conductor TempTypical Use
PVC / thermoplastic (e.g. UK twin & earth 6242Y)70°CDomestic and commercial final circuits
XLPE / thermoset90°CFeeders, industrial power, hot plant rooms
Armoured SWA (steel wire) / AWA (aluminium wire, single-core)70°C (PVC) or 90°C (XLPE)Buried, outdoor and mechanically exposed runs
Flexible rubber (e.g. H07RN-F)60°CPortable equipment, temporary supplies

This calculator does not select by insulation type or armouring. Use it for a first-pass size, then confirm in the table for your exact cable type and installation method.

Applications

Cable Sizing for Motors, Transformers & Long Runs

  • Motor cable size: enter HP with nameplate efficiency and PF. Check starting current and starting voltage drop separately. Some codes add a factor (e.g. NEC 430.22 sizes motor branch conductors at 125% of full-load current).
  • Transformer cable size: secondary current I = (kVA × 1000) ÷ (√3 × V). Enter that value in amps. Large currents often need parallel cables.
  • Long cable runs: voltage drop usually decides the size, not ampacity. Example: 5 kW single phase, 230 V, PF 0.95 → 4 mm² at 25 m, but 10 mm² at 60 m.
  • Aluminium vs copper: aluminium needs roughly one size larger for the same current and drop.
Beyond a single cable

Parallel Cables, Neutral & Earth Sizing, Laying Methods

Field Experience: When Cable Layout Caused the Unbalance (Industrial UPS Connection)

With parallel single-core cables, the way the cables are laid can matter as much as their size. The case below is from site. The layouts drawn further down show the arrangements involved.

  • Situation: an industrial UPS connection was built with parallel single-core cables on each phase. The plant load was almost entirely three-phase, and the single-phase load was negligible.
  • Problem: even though the three-phase load was practically balanced, the unbalanced current was very high. With almost no single-phase load, the load itself could not explain it.
  • Investigation: this was a new problem for me. The load was balanced, so I looked at the cable layout and found that it was the likely cause.
  • Action: the parallel single-core cables were re-laid in the phase-rotated arrangement shown in the trefoil and flat layouts below. Each group carried one complete A-B-C set, the phase order was rotated between groups, and the same order was kept at both ends of the run.
  • Result: after re-laying, the unbalance problem was solved.
  • Why this can happen: in parallel single-core cables, each cable's impedance depends on where it sits relative to the others, because of mutual inductance between the conductors. A poor layout makes some cables carry more current than others, so a balanced load does not guarantee balanced cable currents.
  • Takeaway: if unbalance is high on a three-phase load, check the cable layout as well as the load. Keep the same phase order, group order and cable length at both ends. After laying, clamp-meter every cable at load and compare the cables within each phase. When neutral and earth are included, lay them with the same groups (see the quad and flat-with-neutral layouts below) so every parallel path stays complete.

Single-site experience, not a general rule. If unbalance is high, also rule out other causes such as the load itself, loose terminations and unequal cable lengths.

Parallel Single-Core Cables

  • Used when one conductor per phase would be too large to pull or terminate.
  • Cable arrangement changes mutual inductance — a poor layout makes cables share current unequally.
  • Two families: trefoil (three phases grouped per circuit) and flat (evenly spaced).
  • Follow the layout diagram in the applicable standard (e.g. AS/NZS 3008.1, IEC 60364-5-52) — typically defined for up to four parallel circuits per phase.
ModeSingle-phase (2 conductors)Three-phase (3 conductors)Two conductorsper phaseABBAABCABCThree conductorsper phaseUse a standard-definedsymmetric arrangementABCABCABCFour conductorsper phaseABBAABBAABCABCABCABC

Illustrative example layouts only. Single-phase: flat pairs placed so both conductors of each pair are balanced (A B B A…). Three-phase: each touching trefoil group is one complete A-B-C circuit, so every parallel path has its own set of phases — not a reproduction of any specific standard's published figure. The applicable installation standard (e.g. AS/NZS 3008.1, IEC 60364-5-52) gives the complete, specific set of recommended and alternative arrangements, including additional symmetric options and neutral-conductor placement, for the actual number of parallel conductors in your design.

Parallel Cables per PhaseArrangement ConceptWhy It Matters
1No arrangement choice neededSingle current path
2Same-phase cables close together, evenly placed vs other phasesKeeps mutual inductance similar
3Trefoil per circuit, circuits symmetric, or defined flat sequenceImbalance risk grows with more paths
4Trefoil groups (one A-B-C set per path) or a defined symmetric flat sequence per the standard's diagramArbitrary layouts can split current unevenly

Trefoil vs Flat Layout for 3 Parallel Cables per Phase (Three-Phase)

With three parallel single-core cables per phase there are nine cables in total, laid as three groups. Each group carries one cable of every phase, so each group is a complete three-phase circuit. The two common ways to lay these groups are trefoil and flat.

1. Trefoil groups2. Flat groups (phase order rotated)Group 1ABCA · B · CGroup 2ABCA · B · CGroup 3ABCA · B · CGroup 1ABCA – B – CGroup 2CBAC – B – AGroup 3ABCA – B – CEach group = one complete A-B-C circuitCables touch inside the group, cleatedCables touch inside each group, cleatedSame order at both ends of the runAPhase ABPhase BCPhase C

Illustrative layout only. Phase colours are for identification — use your local colour code. Spacing, cleat pitch and bonding must follow the cable manufacturer and the applicable standard.

1. Trefoil arrangement

Layout: three trefoil groups side by side. Each group holds one A, one B and one C cable, touching and held together with trefoil cleats.

Advantages

  • Low external magnetic field, so less induced heating in nearby steel trays, supports and gland plates.
  • Compact — needs the least tray width.
  • Each group is a complete circuit, so the three paths stay alike when groups are spaced and cut to length equally.
  • Widely used and covered in manufacturer guidance and standards (IEC, IEEE).

Limitations

  • Touching cables lose heat less freely, so the rating can be slightly lower than for spaced flat layouts in some installations.
  • Needs proper trefoil cleats at regular intervals to keep the shape, especially under fault forces.
  • Current sharing between groups is not automatic — it still depends on equal spacing and equal lengths.

2. Flat arrangement (phase order rotated)

Layout: three flat groups of three cables in a row, with the phase order rotated between groups — A-B-C, C-B-A, A-B-C — and the same order kept at both ends.

Advantages

  • Better heat dissipation when cables are spaced, because more of the surface is exposed to air.
  • Rotating the phase order between groups helps even out inductive imbalance, so the parallel paths tend to share current more evenly.
  • Easier to inspect, to clamp-meter each cable and to terminate.
  • Practical on long ladder or tray runs with enough width, where trefoil is awkward.

Limitations

  • Needs more tray width and more mechanical support.
  • Higher external magnetic field than trefoil, so more induced heating in nearby steelwork unless spaced or non-magnetic.
  • Imbalance returns if the rotation is not kept along the whole run and at both ends.
  • Needs correct spacing and cleating as per the manufacturer.

Practical field comparison

ParameterTrefoilFlat (rotated)
Current balanceGoodBetter
Heat dissipationLowerHigher
External magnetic fieldLowerHigher than trefoil
Space requiredLessMore
Installation easeModerateEasier

Field observations, not code values. Results depend on spacing, phase order, bonding and run length.

Key practical points (both arrangements)

  1. Use the same length, material, cross-section, insulation and rating for every parallel cable in a phase.
  2. Keep the A-B-C phase sequence and the group order the same at both ends of the run.
  3. Use cleats and spacing as per the manufacturer and the applicable standard (cable cleats: IEC 61914).
  4. Check induced heating on metal supports and gland plates — pass all cables of one circuit through the same opening, or use a non-magnetic plate.
  5. Verify current sharing after installation with a clamp meter or load test.
  6. Provide sheath bonding and earthing as per the design.
  7. For a calculated current-sharing check, IEC 60287-1-3 covers any number of parallel single-core cables in any layout.

Practical field note: on 3-parallel-per-phase single-core runs, a flat layout with rotated phase order has generally given more even current sharing and easier checking than trefoil in field practice, provided the rotation, spacing and cleating are maintained. Trefoil remains the better choice where space is limited or where the magnetic field near steelwork must stay low. Both are acceptable — follow the project specification and standard, and confirm sharing by measurement.

3. Three-phase with neutral and earth — layout and procedure

This covers a three-phase, four-wire circuit with a separate neutral and separate earth, using three parallel single-core cables per phase. The neutral and earth are laid with the same groups, so each parallel path stays complete.

1. Trefoil becomes a quad (A-B-C-N)2. Flat with neutral and earthGroup 1ABCNEA · B · C · NGroup 2ABCNEA · B · C · NGroup 3ABCNEA · B · C · NGroup 1NABCEN – A – B – CGroup 2NCBAEN – C – B – AGroup 3NABCEN – A – B – CEach group = one A-B-C-N circuit, earth alongsideQuad: 4 cables touching, cleatedNeutral on the same side in every groupPhase order rotated, same order at both endsAPhase ABPhase BCPhase CNNeutralEEarth (CPC)

Illustrative layout only. Neutral and earth sizes, spacing, cleating and bonding must follow the design, the cable manufacturer and the applicable standard.

Neutral options

  • Full-size neutral (default): same size as the phase cable, one neutral per group. Every group then carries the same share of neutral current. Prefer this with non-linear loads (triplen harmonics).
  • Reduced neutral: only where the load is balanced, low in harmonics and the standard allows it. Use fewer neutral cables of equal size, place them symmetrically and check the sharing by measurement.

Earth options

  • Separate earth conductor(s) (green-yellow) on the same route, close to the phase cables — one per group or a common conductor. Size for fault current and disconnection time with the Earthing Conductor Size Calculator.
  • Armour, sheath or tray as the protective conductor only where the design and standard permit it, after checking continuity and impedance.

Procedure

  1. Fix the number of parallel paths and the layout first (quad or flat) — the neutral and earth follow the same layout.
  2. Select the neutral size. Default is the same size as the phase; reduce it only where the conditions above are met.
  3. Lay one neutral with each group, with the same length, material and size as the phase cables. In a trefoil layout this makes a quad bundle; in a flat layout keep the neutral in the same position in every group.
  4. Size the earth conductor for the fault current and disconnection time, then lay it on the same route, close to the groups.
  5. Cleat each group with the correct trefoil or quad cleats as per the manufacturer, with the earth conductor alongside.
  6. Terminate phase, neutral and earth in the same order at both ends. Land the neutrals on the neutral bar and the earth on the earth bar.
  7. Provide sheath or armour bonding as per the design. In large single-core cables, bonding both ends can cause circulating current, so check it at design stage.
  8. Before energising: insulation resistance, phase-sequence and neutral/earth continuity checks.
  9. After energising: clamp-meter each phase and neutral cable in every group, and check the glands, plates and supports for heating.

Neutral Conductor Sizing

  • Default: neutral = phase conductor size (this is what the calculator shows).
  • Balanced, low-harmonic 3-phase loads: a reduced neutral may be allowed — it must still carry the out-of-balance current.
  • Many nonlinear single-phase loads (LED drivers, SMPS, IT equipment): triplen harmonics (3rd, 9th…) add in the neutral — size it equal to or larger than the phase.

Earth / CPC Conductor Sizing

  • Rule of thumb used here: same as phase up to 16 mm², 16 mm² for 16–35 mm², half the phase size above 35 mm².
  • Final design needs the adiabatic check (fault current and disconnection time) — use the Earthing Conductor Size Calculator.

Common Cable Laying Methods

Laying MethodTypical ApplicationKey Consideration
Clipped direct / cleatedShort exposed runs, utility wiringSpacing from surface affects rating
Conduit or trunkingFinal circuits in walls, ceilingsRestricted airflow; cables per conduit derate
Perforated tray / ladderSwitchrooms, industrial plantsGood airflow; touching vs spaced matters
Free air, spacedWhere highest rating is neededNeeds real spacing to achieve free-air rating
Direct in groundUnderground feeders (usually SWA)Soil resistivity and depth control rating
Ducts in groundUnderground runs needing re-pullingAir in duct lowers rating vs direct burial
Aerial / messenger wireService to remote structuresMechanical support, clearance, weather

Laying Method Diagrams: Tray, Direct Buried and Ducts

The same cable carries a different current depending on how it is laid, because the laying method decides how easily heat leaves the cable. The three cross-sections below show the methods in the table above that most often decide the derating factor.

1. Perforated tray / ladder

Perforated cable tray — cross-sectionTouching (bunched)Spaced (≥ 1 × cable dia.)≥ DeHeat builds up between cables→ grouping derating appliesAir flows between cables→ closest to free-air ratingPerforations in the tray base let heat escape from below
  • Touching: bunched cables heat each other, so a grouping factor applies.
  • Spaced: a gap of at least one cable diameter (De) lets air move between cables and gets closest to the free-air rating.
  • In the IEC / BS reference methods, multicore cable on perforated tray is Method E, single-core touching is Method F and single-core spaced is Method G. Check the exact conditions in your standard's table.
  • Keep cables in a single layer where possible; extra layers add more derating.

2. Direct buried

Direct buried cable — trench cross-sectionDepthto cable≈ 0.5–0.8 mNative groundGround surfaceBackfill (excavated soil)Warning tapeCable cover tile / slabSand beddingArmoured cable
  • The rating depends on burial depth, ground temperature and soil thermal resistivity. Published tables commonly assume about 0.7 m depth, 20 °C ground and 2.5 K·m/W soil, so dry or sandy soil needs a derating factor.
  • Sand bedding protects the sheath and carries heat away; the cover tile and warning tape protect against later excavation.
  • Other cables or heat sources nearby also reduce the rating; groups of buried circuits need a grouping factor.

3. Ducts in ground

Ducts in ground — duct bank cross-sectionDepthto topof ductGround surfaceBackfillConcrete encasementDuct (PVC / HDPE)Spare duct, future cableMulticore cable3 single-core in 1 duct
  • The air inside a duct resists heat flow more than soil does, so the same cable has a lower rating in a duct than direct buried.
  • Ducts let you pull or replace cables without digging; spare ducts and draw pits make later additions easy.
  • For single-core cables, keep all phases of a circuit together in the same non-magnetic duct. Putting one phase in each steel duct causes heating and unequal current.

Illustrative cross-sections, not to scale. Depths, spacing and bedding are typical values only; follow your standard, the cable manufacturer and the utility specification. For the derated current, use the Current Carrying Capacity Calculator.

Cable Laying & Installation Checklist

The calculator gives a preliminary size only. Before and during installation, confirm these points against the project specification and the applicable standard.

ItemWhat to verify
Route surveyCable route, length, and whether it is underground, overhead or on tray
Cable selectionVoltage rating, conductor material, insulation type and number of cores
InstallationMinimum bend radius, pulling tension and drum handling
Cable supportCleat spacing, tray loading and mechanical protection
DeratingAmbient temperature, grouping, soil conditions and thermal insulation
EarthingArmour bonding, earth continuity and fault protection
TerminationCorrect glands and lugs, phase identification and tightening torque
TestingInsulation resistance, continuity, phase sequence and the required commissioning tests

A general engineering checklist — requirements differ between installations and are not identical for every cable.

Common Cable Sizing Mistakes

  • Ignoring length: a cable rated for the current can still fail the voltage-drop check.
  • Assuming PF = 1 for motors: underestimates current and undersizes cable and breaker.
  • Skipping derating: hot rooms and grouped cables reduce capacity.
  • Ignoring cores / loaded conductors: 2-, 3- and 4-core cables have different ratings (not modelled here).
  • Swapping Cu ↔ Al without re-checking the size table.

Conceptual background only. For final design use the applicable standard (AS/NZS 3008.1/3000, IEC 60364-5-52, IS installation practice or BS 7671) and verify with a qualified electrical engineer.

FAQ

Cable Size Calculator — Frequently Asked Questions

Content last reviewed: October 2026

How do I calculate cable size? +

Find the load current with I = (kW × 1000) ÷ (V × PF) for single phase or I = (kW × 1000) ÷ (√3 × V × PF) for three phase. Choose the smallest cable (mm²) whose current-carrying capacity, after derating, is at least that current. Then check voltage drop over the cable length and step up one size if the drop is too high.

How do I calculate cable size for a 3 phase load? +

Select Three Phase, enter the line-to-line voltage (e.g. 400 V or 415 V), load in kW, HP or A, power factor and cable length. The calculator uses I = (kW × 1000) ÷ (√3 × V × PF), picks the smallest size whose reference capacity × derating factor covers the design current, then checks voltage drop with Vd = √3 × I × L × (R cosφ + X sinφ) ÷ 1000 at the selected conductor temperature and steps up if needed.

What size cable do I need for a 10 kW three-phase load? +

At 415 V and PF 0.85, a 10 kW load draws about 16.4 A. In this calculator's screening model, that gives 4 mm² copper for a 30 m run with about 1.0% voltage drop at a 70°C conductor temperature. Longer runs, derating or a different installation method can require a larger size.

Why does cable length change the recommended size? +

Longer cables have more resistance and reactance, so voltage drop rises in proportion to length. For example, a 5 kW single-phase load at 230 V (PF 0.95) screens at 4 mm² copper for 25 m, but needs 10 mm² at 60 m to stay under the 3% screening target (70°C conductor temperature).

Which decides the cable size — current capacity or voltage drop? +

Both are checked and the larger resulting size wins. Current-carrying capacity (after derating) protects the insulation from overheating; voltage drop protects the equipment at the far end. On short runs the capacity check usually governs; on long runs voltage drop usually forces a larger size than capacity alone would need. The calculator shows which criterion governed in the comparison table.

Why does the voltage drop depend on conductor temperature and power factor? +

Copper resistance rises by about 20% between 20°C and 70°C, so a fully loaded cable drops more voltage than a cold-resistance calculation suggests. On AC circuits the drop also includes the cable reactance, weighted by the load power factor: Vd per unit length ∝ R cosφ + X sinφ. For small cables resistance dominates; for large cables at low power factor the reactance term becomes significant.

What is current-carrying capacity (ampacity)? +

It is the maximum continuous current a cable can carry without exceeding its insulation temperature limit — for example 70°C for PVC or 90°C for XLPE. It depends on installation method, ambient temperature and grouping, so the tabulated value must be corrected with derating factors.

Why does aluminium need a larger cable size than copper? +

Aluminium has lower conductivity than copper, so it needs a larger cross-section for the same current and voltage drop — usually about one standard size larger.

Can I use this as a UK or BS 7671 cable size calculator? +

Yes, for a preliminary size: select 230 V single phase or 400 V three phase. The result uses simplified screening values, not BS 7671 Appendix 4 tables, so confirm the final size against BS 7671 for your installation method and cable type (e.g. twin & earth or SWA).

Does this calculator cover armoured (SWA) or XLPE cables? +

Not directly — it gives one screening size per conductor material. To apply PVC 70°C or XLPE 90°C insulation, installation method, grouping and ambient derating, enter the base ampacity from your SWA/XLPE cable table in the Current Carrying Capacity Calculator.

How is the protective-device (MCB/MCCB) rating chosen? +

The calculator picks a standard rating that satisfies Ib ≤ In ≤ cable capacity. It is indicative only — final selection must also check fault level, breaking capacity, trip curve and coordination.

What size should the neutral and earth conductor be? +

Neutral defaults to the same size as the phase; increase it where many nonlinear single-phase loads cause triplen harmonics. Earth/CPC uses a rule of thumb (same as phase up to 16 mm², 16 mm² for 16–35 mm², half above 35 mm²); verify with an adiabatic calculation.

Does this replace a full cable sizing study? +

No. It is a preliminary estimate. Final design must include derating, installation method, harmonics, fault-level checks and your local wiring code, ideally reviewed by a qualified electrical engineer.