Blog · Electrical · Interview Questions · Part III

Electrical Interview Questions Part III: PLC, Reliability, UPS, HV, DG & ACB

Calculate Smarter. Work Faster.

40 practical questions (Q81–Q120) on PLC, reliability, UPS, HV, DG, boiler & ACB — each with a definition, formula, key points and a model answer, plus linked calculators for every module.

40 questions7 modules

Created by Umasankar Maity — B.Tech in Electrical Engineering, with 11+ years of industrial maintenance experience.

Reviewed by the ElectroMechCalc editorial team.

Last reviewed: September 2026  |  Standards referenced: IEC 60034; IEC 60947-2; IEC 60076; IEC 60364 / BS 7671; IEEE 43; IEC 60422; IEC 62040; ISO 8528; NEMA MG 1

About Part III

Part III covers PLC and automation, maintenance management and reliability, UPS systems, 11/33/66 kV systems, DG sets, boiler electrical and control, and ACB protection and testing — questions 81 to 120 of the 120-question series. Each answer gives a short definition, the formula where one applies, the key points an interviewer listens for, and a first-person model answer to adapt with your own plant experience.

Values such as test voltages, acceptance limits and protection settings are typical; the equipment manufacturer's data and the standards that apply at your site always take priority. Breakdown and automation questions in this part are best answered in the same safe order:

  1. Safety & LOTO
  2. Symptom / trip indication
  3. Measure
  4. Separate electrical vs mechanical
  5. Root cause
  6. Repair
  7. Test
  8. Controlled restart
  9. Document & RCA

Calculators and guides that match each module are listed at the end of it, and the full list of questions from the other parts is at the bottom of this page.

No question matches that filter. Try a shorter term, such as “motor” or “relay”.

Module 8 · Q81–Q90

PLC & Industrial Automation

PLC architecture, I/O troubleshooting, logic, communication, I/O mapping and backups.

Q81

What is a PLC?

Definition

A programmable logic controller is an industrial computer that reads inputs, executes a program cyclically (the scan cycle) and controls outputs.

Modular PLC rack

Main components

  • CPU
  • Memory
  • Power supply
  • Digital inputs/outputs
  • Analog inputs/outputs
  • Communication modules

Model interview answer

“A PLC continuously reads field inputs, executes the program and updates outputs. During troubleshooting I separate the problem into field device, I/O, logic, communication and output-device sections.”

Q82

How do you troubleshoot PLC digital I/O?

Sequence

Field device → Wiring → Terminal → PLC I/O (LED + status) → Logic → Output device
Digital I/O trace path

Model interview answer

“I start at the field device and follow the signal through wiring, terminal, PLC input LED and PLC status. For an output I trace from PLC logic to output module, relay/contactor and finally the field device.”

Q83

How do you troubleshoot PLC analog I/O?

Analog input loop wiring

Model interview answer

“I verify the transmitter's 24 V supply and the actual 4–20 mA signal first. Then I check cable polarity, terminals, analog input configuration (range, 2-wire/4-wire), scaling, and grounding/shielding. Finally I compare the PLC value with the measured signal.”

Q84

How do you troubleshoot PLC logic?

Ladder rung: find the first open condition

Key areas

  • Inputs
  • Permissives
  • Interlocks
  • Timers
  • Counters
  • Sequence steps
  • Outputs
  • Alarms

Model interview answer

“I identify the exact sequence step where the machine stopped, then find the first missing condition or permissive in the logic, using online monitoring. I never bypass or force a safety interlock just to make the machine run.”

Q85

What causes PLC communication failure?

Where communication breaks

Possible causes

  • Cable or connector fault
  • Network switch failure
  • Wrong IP/node address
  • Duplicate IP
  • Configuration mismatch
  • Power failure
  • Module failure
  • Electrical noise, poor shielding or grounding

Model interview answer

“I first check power and the physical link, then network status, address and configuration and PLC/module diagnostics. If communication is intermittent, I also check shielding, grounding and noise sources.”

Q86

What is HMI–PLC communication?

Definition

The HMI provides the operator interface — process values, alarms, commands and status — while the PLC performs the control logic.

Find which layer shows the wrong value

Model interview answer

“If an HMI value is wrong, I determine whether the problem is in the field signal, the PLC value, the communication tag or HMI scaling. A wrong HMI display does not automatically mean the field instrument is faulty.”

Q87

What is PLC I/O mapping?

Definition

I/O mapping assigns physical field devices to PLC addresses/tags and links them to the control logic.

Sequence

Sensor → DI → PLC logic → DO → Contactor → Motor
I/O mapping: device → terminal → address → tag

Model interview answer

“Incorrect I/O mapping can make a healthy field device look faulty. I verify the actual terminal, PLC address, tag and program logic before changing hardware.”

Q88

An automatic machine sequence stops. How do you troubleshoot it?

Machine halted at step 4

Model interview answer

“I identify the exact sequence step and check the required sensor inputs, permissives and interlocks. If an input is missing, I troubleshoot the field device. If inputs are healthy, I check PLC logic and output, then follow the output through relay, contactor or solenoid to the machine.”

Q89

What should be included in a PLC backup?

What a complete backup contains

Key points

  • PLC program (with comments/symbols)
  • HMI/SCADA project
  • Hardware configuration
  • Network configuration
  • VFD parameters
  • Instrument/transmitter parameters
  • Version and date
  • Communication settings

Model interview answer

“I maintain a controlled backup of PLC and HMI programs together with VFD and network parameters, with version information, so the correct program can be restored quickly after a hardware failure.”

Q90

Explain complete automation troubleshooting.

Sequence

Field sensor → Wiring → PLC input → PLC logic → PLC output → Relay/contactor → Actuator → Machine
Automation troubleshooting chain

Model interview answer

“At every stage I take an actual measurement or diagnostic indication. This quickly separates field, electrical, PLC and mechanical problems.”

Module 9 · Q91–Q100

Maintenance Management & Reliability

PM, PdM, RCA, job planning, spares, MTBF/MTTR and reliability improvement.

Q91

What are preventive, predictive and breakdown maintenance?

P–F curve: preventive vs predictive

Definitions

  • Preventive: planned maintenance based on time or usage.
  • Predictive: condition-based maintenance driven by measured data.
  • Breakdown (corrective): repair after failure.

Model interview answer

“My objective is to reduce unplanned breakdowns with the right mix of PM and PdM. For critical equipment I prefer condition monitoring and trend-based intervention wherever practical.”

Q92

How do you prepare an electrical PM schedule?

Criticality drives PM frequency

Key points

  • Equipment criticality
  • OEM recommendations
  • Operating hours and duty
  • Failure history
  • Safety and statutory requirements
  • Inspection/testing frequency

Model interview answer

“I classify equipment by criticality, then define inspection, testing and servicing frequencies. Motors, MCCs, transformers, VFDs, batteries, cables, earthing and protection systems are included according to their risk and operating conditions.”

Q93

What is predictive maintenance?

Definition

Predictive maintenance uses equipment condition data to decide when intervention is needed.

Condition trend gives early warning

Methods

  • Thermography
  • Vibration analysis
  • IR/PI trending
  • Oil analysis and DGA
  • Temperature trending
  • Motor current signature analysis
  • Ultrasound

Model interview answer

“I use trends rather than only fixed intervals. For example, rising motor bearing temperature or vibration gives an early warning before a breakdown.”

Q94

What is RCA?

Definition

Root cause analysis identifies the fundamental reason for a failure rather than only correcting the immediate symptom.

Fishbone diagram for RCA

Methods

  • 5 Why
  • Fishbone (Ishikawa)
  • Fault tree analysis
  • Trend analysis
  • Failure history review

Model interview answer

“If a motor bearing repeatedly fails, replacing the bearing is corrective action, not root-cause correction. I investigate lubrication, alignment, vibration, shaft condition, coupling and load. If misalignment is the root cause, I correct alignment and then monitor vibration and temperature.”

Q95

How do you plan a maintenance job?

Maintenance job planning

Key points

  • Scope
  • Manpower and skills
  • Tools and test instruments
  • Spares
  • Safety, PTW and LOTO
  • Shutdown window
  • OEM requirements
  • Testing and restoration plan

Model interview answer

“Before a critical job I prepare manpower, tools, spares, drawings, safety requirements and test instruments. Good planning reduces downtime and prevents equipment sitting open because a critical spare or tool is missing.”

Q96

How do you manage electrical spare parts?

Definition

Spares management keeps critical parts available when needed without excess inventory.

Min/max stock control

Key points

  • Critical spares
  • Fast-moving items
  • Long-lead items
  • Min/max stock levels
  • Lead time
  • Obsolescence
  • Consumption history

Model interview answer

“I classify spares by equipment criticality and lead time. Critical breakers, contactors, overloads, VFDs, PLC modules, fuses and sensors may need strategic stocking depending on plant risk.”

Q97

Explain MTBF and MTTR.

Formula

MTBF = Total operating time / Number of failures MTTR = Total repair time / Number of repairs Inherent availability = MTBF / (MTBF + MTTR)
Up time, down time, MTBF and MTTR

Model interview answer

“MTBF shows equipment reliability, while MTTR shows how quickly we restore equipment after a failure. If MTBF is falling, I look for recurring failure modes and RCA. If MTTR is high, I look at manpower, access, troubleshooting time, procedures and spares availability.”

Q98

How can you improve electrical equipment reliability?

Reliability improvement shows in the data

Key points

  • Criticality analysis
  • PM and PdM
  • RCA
  • Thermography
  • Vibration monitoring
  • IR testing
  • Correct protection settings
  • Correct cable sizing
  • Critical spares
  • PLC/VFD backups

Model interview answer

“My focus is preventing failures rather than only responding to them. I use condition monitoring, RCA, proper protection, critical spare planning and historical data, and measure improvement through reduced breakdown frequency, downtime and repeat failures.”

Q99

How do you manage a major plant electrical breakdown?

Sequence

Safety → LOTO → Diagnosis → Manpower → Spares → Repair → Testing → Restoration → Monitoring → RCA
Major breakdown response

Model interview answer

“During a major breakdown my first priority is personnel and equipment safety. After isolation I establish the fault, mobilise manpower and spares, execute the repair and test properly before a controlled restoration. After stabilisation I document the event and perform RCA if the failure is critical or repetitive.”

Q100

What is your approach as a senior electrical maintenance engineer to improve plant reliability?

Continuous reliability improvement

Strong closing line

“I don't want to be only a breakdown responder; I want to make the equipment more reliable so that the same failure doesn't happen again.”

Model interview answer

“My approach isn't limited to restoring equipment after a breakdown. I focus on equipment criticality, preventive and predictive maintenance, RCA of repeated failures, condition monitoring, critical spare planning, protection coordination, PLC/VFD backups and MTBF/MTTR improvement. I coordinate closely with production and safety teams. My objective is higher availability, lower unplanned downtime, safe operation and continuous improvement.”

Module 10 · Q101–Q104

UPS Systems

UPS topologies, UPS vs inverter, battery backup estimation and bypass systems.

Q101

What is a UPS? Explain its working principle and major components.

Definition

A UPS (uninterruptible power supply) provides continuous power to critical loads even when the normal AC supply fails or becomes abnormal.

Sequence

Normal: AC supply → Rectifier/charger → DC bus → Inverter → Critical load | Mains failure: Battery → DC bus → Inverter → Critical load
Online double-conversion UPS

Main components

  • Rectifier/charger
  • DC bus
  • Battery bank
  • Inverter
  • Static bypass
  • Maintenance bypass
  • Control and protection system

Maintenance focus

Battery voltage and health, DC bus, rectifier, inverter, cooling fans, bypass operation, alarm history and output voltage/frequency.

Model interview answer

“An online (double-conversion) UPS continuously supplies the critical load through its inverter. Normally the rectifier converts AC to DC and charges the battery while the inverter feeds the load. On mains failure the battery immediately supports the DC bus and the inverter continues without interruption. If the inverter faults or is overloaded, the static bypass transfers the load to the bypass source.”

Q102

Explain online, offline and line-interactive UPS. How does a UPS differ from an inverter?

Definition

A UPS is designed for uninterrupted, conditioned power to critical loads. An inverter (in the home/backup sense) mainly converts battery DC to AC during an outage.

FeatureOnline (double-conversion)Line-interactiveOffline (standby)Home/backup inverter
Normal load pathThrough the inverter continuouslyMains, with AVR tap-changingMainsMains via changeover relay (typical)
Transfer on mains failureNo transfer — zero breakShort transfer (a few ms)Short transfer (typically a few ms)Longer changeover, design-dependent
Voltage conditioningExcellentModerateLimitedDepends on model
Typical usePLC, servers, instrumentationSmall IT and office loadsNon-critical PCsHomes, general backup loads
Output continuity on mains failure

Model interview answer

“The main difference is architecture and application. An online UPS continuously powers the load through its inverter, so it suits sensitive PLC, automation and instrumentation loads. A conventional inverter mainly provides backup conversion from battery DC to AC and may not give the same power conditioning or seamless transfer.”

Q103

How do you calculate UPS battery backup time? What affects it?

Formula

Backup (h) ≈ (N × V_battery × Ah × η_inverter × DoD) / Load (W)

N = number of batteries in the string, DoD = usable depth of discharge. This is a first estimate; high discharge rates reduce effective Ah (Peukert effect).

What sets UPS backup time

Factors

  • Load in watts
  • Battery voltage and Ah
  • Battery age and condition
  • Temperature
  • UPS/inverter efficiency
  • Discharge rate
  • Number and configuration of batteries
  • End-of-discharge voltage setting

Model interview answer

“I calculate theoretical backup from battery energy and load, but actual backup is lower because of inverter efficiency, ageing, temperature and discharge characteristics. For accurate figures I use the battery manufacturer's constant-power discharge tables. During maintenance I check individual battery voltage, terminal condition, temperature and overall bank health.”

Q104

What are UPS bypass systems? Explain static and maintenance bypass.

Definition

A bypass provides an alternative path to supply the critical load without passing through the UPS inverter.

Static and maintenance bypass paths

Types

  • Static bypass — automatic electronic transfer
  • Maintenance (manual) bypass — isolates the UPS for servicing

Important

Before operating any bypass, verify synchronisation, source availability, load condition and the approved switching procedure — a wrong switching sequence can drop the critical load.

Model interview answer

“Static bypass is an automatic electronic transfer path used during UPS overload, inverter failure or certain abnormal conditions. Maintenance bypass provides a safe alternative supply so the UPS can be isolated for maintenance while the load stays energised, where the system architecture allows.”

Module 11 · Q105–Q108

High-Voltage Systems (11 kV / 33 kV / 66 kV)

Why distribution uses higher voltages, current at different voltage levels, 11 kV protection and commissioning.

Q105

Why are 11 kV, 33 kV and 66 kV used in distribution? Why '11' kV and not 10 kV?

Definition

11 kV, 22 kV, 33 kV, 66 kV, 132 kV and 220 kV are standardised nominal voltages used in India, the UK and many Commonwealth-influenced networks. Other regions use different levels — for example 10/20 kV in much of continental Europe and 12.47/13.8/34.5 kV in North America.

Formula

P = √3 × V × I × PF For the same power: I ∝ 1 / V Conductor loss: P_loss = 3 × I² × R Classic explanation: sending-end V ≈ 1.1 × receiving-end V (10 kV × 1.1 = 11 kV)

Raising voltage reduces current for the same power, which reduces I²R losses (by the square of the current ratio) and voltage drop.

Receiving end (nominal)10 kV20 kV30 kV60 kV120 kV200 kV
Sending end (+10%)11 kV22 kV33 kV66 kV132 kV220 kV
Typical voltage stages (India/UK style)

Points to cover

  • The widely taught explanation: lines were designed so that roughly 10% extra voltage at the sending end covers the voltage drop along the line, so a line delivering about 10 kV is sent at 11 kV. The same pattern gives 22, 33, 66, 132 and 220 kV.
  • Why about 10%: voltage drop varies with load current, so a round allowance was chosen for typical line lengths and loading — not an exact calculated figure.
  • It is not the form factor (1.11): 10 kV × 1.11 = 11.1 kV and 120 kV × 1.11 = 133.2 kV, which do not match the real 11 kV and 132 kV levels. Form factor (RMS ÷ average of a sine wave) is unrelated.
  • Not every level is a multiple of 11: 400 kV, 765 kV and 800 kV are not. These EHV levels came from later standard voltage series, and such networks hold voltage with reactive compensation and voltage control rather than a fixed 10% margin.
  • The same idea shows up at LV: distribution transformer secondaries are often rated slightly above the nominal system voltage at no load (for example 433 V on a 415 V system) to allow for regulation under load.
  • Why the levels stayed: once breakers, transformers, insulators and cables were standardised around these ratings, adding new levels (44, 55, 77 kV…) would add cost and complexity without much benefit.

Interview tip

Present the 10% voltage-drop reason as the classic explanation, then show depth by rejecting the form-factor myth and noting that 400/765 kV and non-Commonwealth levels such as 10/20 kV or 13.8 kV don't follow the pattern. Actual standard voltages are listed in IEC 60038 and national standards.

Model interview answer

“11 kV is a standardised distribution voltage. The commonly accepted reason for the '11' is that about 10% extra voltage is sent to cover line voltage drop, so a nominal 10 kV at the receiving end is sent at 11 kV — the same logic gives 22, 33, 66, 132 and 220 kV. It is not related to the 1.11 form factor, and it doesn't apply to EHV levels like 400 or 765 kV, where voltage is controlled with compensation. Higher voltage is used for the same power because current falls, which reduces I²R loss and voltage drop.”

Q106

Calculate current at 11 kV, 33 kV and 66 kV for the same power.

Formula

I = P / (√3 × V × PF) 10 MW, PF = 1 at 11 kV: I ≈ 525 A at 33 kV: I ≈ 175 A at 66 kV: I ≈ 87.5 A

Check: 10,000,000 ÷ (1.732 × 11,000) = 524.9 A. At PF 0.9 each current rises by a factor of 1/0.9.

Same power, higher voltage, lower current

Maintenance focus

Transformer ratio, HV insulation, protection, cable terminations, VCB, CT/PT and earthing.

Model interview answer

“The same power needs about one-third of the current when voltage rises from 11 kV to 33 kV, and about one-sixth at 66 kV, at the same power factor. Because loss is proportional to I², going from 11 kV to 33 kV cuts conductor loss to about one-ninth for the same conductor.”

Q107

Explain an 11 kV system, its equipment and protection arrangement.

Sequence

33 kV incoming → 33/11 kV transformer → 11 kV VCB → 11 kV bus → Outgoing feeders → Transformers / HV motors
11 kV single-line diagram

Major equipment

  • Power transformer
  • VCB
  • CT/PT
  • Protection relay
  • Busbar
  • 11 kV cable
  • Surge arrester
  • Earthing system

Protection

Overcurrent and earth fault (including sensitive/restricted earth fault), transformer differential where applicable, Buchholz and temperature for transformers, and under/over-voltage where required.

Model interview answer

“On an 11 kV feeder fault I expect the VCB to trip via the protection relay. I read relay indications and event records first, then check the cable, termination, transformer or connected load depending on the fault location. Before re-energisation, insulation and other required tests must be completed.”

Q108

How do you test and commission an 11 kV cable or transformer before energisation?

Pre-energisation checks

Cable checks

Visual inspection, continuity and phase identification, insulation resistance, sheath test where applicable, termination inspection, earth continuity and the specified HV withstand test (e.g. VLF), per the applicable standard and cable manufacturer.

Transformer checks

IR, winding resistance, turns ratio, vector group, magnetising current, oil tests where applicable, protection and alarm checks, earthing, tap position and functional checks.

Model interview answer

“I follow the approved commissioning checklist and the applicable standard/OEM requirements. I verify mechanical condition, insulation, connections, earthing, protection and functional operation. Only after satisfactory results and formal authorisation do I proceed with controlled energisation.”

Module 12 · Q109–Q114

DG Sets (Diesel Generators)

DG working principle, AVR vs governor, synchronisation, load sharing, reverse power and troubleshooting.

Q109

Explain the working principle of a DG set.

Definition

A DG set converts chemical energy in diesel fuel into mechanical energy in the engine, and the alternator converts that into electrical energy.

Sequence

Diesel fuel → Engine → Mechanical rotation → Alternator → Electrical power
DG set energy flow

Major components

  • Diesel engine
  • Alternator
  • AVR
  • Governor
  • Fuel system
  • Cooling system
  • Lubrication system
  • Starting battery
  • Control panel
  • Protection system

Model interview answer

“The engine provides torque to rotate the alternator. The AVR controls excitation and therefore voltage, and the governor controls engine speed and therefore frequency. I monitor voltage, frequency, oil pressure, coolant temperature, battery condition and load.”

Q110

What are an AVR and a governor? How do they differ?

Formula

f = P × N / 120 (from Ns = 120f / P)

Example: a 4-pole alternator runs at 1500 rpm for 50 Hz or 1800 rpm for 60 Hz.

AVR controls voltage, governor controls frequency

AVR (automatic voltage regulator)

Controls alternator excitation to hold output voltage.

Governor

Controls fuel to the engine to hold speed, which sets frequency.

Model interview answer

“If DG voltage is unstable I investigate the AVR and excitation system. If frequency is unstable I investigate engine speed, governor and load response. I don't mix up the two because they control different parameters.”

Q111

What is DG synchronisation? What must match before paralleling?

Definition

Synchronisation connects a generator to a live bus after matching its electrical conditions to the bus.

Synchroscope before closing the DG breaker

Conditions

  • Voltage magnitude
  • Frequency (incoming set typically slightly faster so it picks up load)
  • Phase sequence
  • Phase angle
  • Synchronising permissive/interlock (check-sync)

Model interview answer

“Before closing the DG breaker onto a live bus, voltage, frequency, phase sequence and phase angle must be within limits. After synchronisation, active power (kW) is controlled mainly through the governor/load-sharing system and reactive power (kVAR) through excitation/AVR.”

Q112

What are DG load sharing and reverse power protection?

Load sharing and reverse power

Load sharing

When generators run in parallel, total kW and kVAR are shared between them — kW via governors (droop or isochronous load sharing) and kVAR via AVRs (droop or VAR sharing).

Reverse power

Power flowing from the bus into a generator, so it runs as a motor driving its own engine.

Possible causes of reverse power

Engine fuel starvation, governor problems, loss of prime-mover power or incorrect load-sharing operation.

Model interview answer

“During parallel operation the governor/load-sharing system controls real power sharing and excitation controls reactive power sharing. Reverse power protection trips the generator breaker to stop a generator being motored if its prime mover loses power.”

Q113

A DG has low voltage, unstable frequency, high temperature or low oil pressure. How will you troubleshoot it?

DG symptoms and where to look

Low voltage

AVR, excitation, sensing connections, alternator condition, load and engine underspeed.

Frequency problem

Governor, engine speed, fuel system and sudden load changes.

High temperature

Overload, coolant level, radiator, fan and belt, airflow and ambient temperature.

Low oil pressure

Oil level, filter, pump, leaks, engine condition and the pressure sensor itself.

Model interview answer

“I first identify the exact alarm or trip and record operating parameters. I separate electrical faults from engine faults. I never bypass low-oil-pressure or high-temperature protection to keep the DG running, because those protections prevent major engine damage.”

Q114

What DG protections are important? How do you troubleshoot a DG starting failure?

Sequence

Battery → Starter → Fuel → Cranking → Controls → Safety interlocks
DG starting failure checks

Important protections

  • Over/under voltage
  • Over/under frequency
  • Overcurrent and short circuit
  • Earth fault
  • Reverse power
  • Low oil pressure
  • High coolant temperature
  • Overspeed
  • Emergency stop

Model interview answer

“If the DG doesn't start, I check battery voltage and terminals, starter operation, emergency-stop status, fuel availability, control fuses and starting permissives. Then I check whether the engine cranks but doesn't fire, or doesn't crank at all — that immediately separates the fault category.”

Module 13 · Q115–Q118

Boiler — Electrical & Control

Boiler electrical equipment, draft fans, feed pumps, interlocks and three-element drum-level control.

Q115

Explain the working principle of an industrial boiler and its major electrical equipment.

Definition

A boiler converts water into steam using heat from fuel combustion or another heat source.

Boiler: fans, feed pump and controls

Major electrical/automation equipment

  • FD fan
  • ID fan
  • PA fan where applicable
  • Feed-water pump
  • Burner and ignition system
  • Motors with VFDs/starters
  • PLC/BMS and HMI
  • Level, pressure and temperature transmitters
  • Solenoid valves
  • Safety interlocks and flame scanner

Model interview answer

“From an electrical perspective I focus on reliable operation of fans, feed pumps, burner systems, VFDs, PLC I/O and instrumentation. Boiler operation is heavily interlocked, so electrical and instrumentation reliability directly affects plant safety.”

Q116

Explain ID fan, FD fan, PA fan and feed-water pump. What electrical problems occur?

Air and flue gas path through fans

Common electrical problems

  • Motor overload
  • Bearing failure
  • VFD fault
  • Single phasing
  • Cable fault
  • Contactor/ACB/MCCB trip
  • Voltage imbalance

FD fan

Forced draft — supplies combustion air.

ID fan

Induced draft — extracts flue gas and maintains furnace draft.

PA fan

Primary air — carries/dries fuel where the firing system needs it (e.g. pulverised coal, some fluidised-bed boilers).

Feed-water pump

Supplies water to the boiler drum against drum pressure.

Model interview answer

“If an ID fan motor trips, I check current, voltage, VFD/breaker status, bearings, damper position, fan vibration and mechanical load. For a feed-water pump I also check process conditions such as suction and discharge pressure, and whether the pump is mechanically loaded correctly.”

Q117

What are boiler interlocks and trips? Why must they never be bypassed?

Definition

Interlocks allow equipment to operate only when safe conditions are satisfied. Trips shut down equipment or the process when a dangerous condition occurs.

Boiler permissives into one enable

Examples

  • Low drum water level
  • High steam pressure
  • Flame failure
  • Fan failure
  • Feed-water failure
  • High temperature
  • Emergency stop
  • Purge not complete

Model interview answer

“Boiler interlocks are safety-critical. If a permissive is missing, I find the actual cause through the sensor, wiring, PLC logic and actuator. I do not bypass a safety interlock to restart the boiler, because it may be preventing a dangerous condition such as a furnace explosion or low-water damage.”

Q118

What is three-element drum-level control?

Definition

Three-element control uses drum level, steam flow and feed-water flow together to control drum level during changing steam demand.

Three-element drum level control

Maintenance focus

Level transmitter and its density compensation, steam-flow and feed-water-flow measurement, PLC/DCS logic, control valve and signal scaling.

Model interview answer

“Single-element control responds only to drum level. Three-element control adds steam flow as a feed-forward and feed-water flow as a cascade loop, improving response to load changes and compensating for shrink and swell — where level temporarily moves the 'wrong' way during a load change.”

Module 14 · Q119–Q120

ACB Protection & Testing

LSIG protection, breaking capacity ratings, spring charging, interlocks and injection testing.

Q119

Explain ACB construction and LSIG protection.

Definition

An ACB is a high-current LV circuit breaker that uses air as the arc-interrupting medium, with main and arcing contacts, arc chutes, a stored-energy mechanism and an electronic trip unit.

LSIG trip curve regions (illustrative)

L — Long time

Protects against sustained overload (inverse-time).

S — Short time

Delayed short-circuit protection that allows downstream devices to clear first (selectivity).

I — Instantaneous

Trips without intentional delay for very high fault current.

G — Ground/earth fault

Detects earth-fault current — residual or neutral-return sensing, depending on the arrangement.

Model interview answer

“Electronic trip units let protection be set according to the feeder and the coordination study. I check long-time pickup, short-time pickup and delay, instantaneous setting and earth-fault settings, keeping them within the equipment and coordination requirements.”

Q120

What are ACB Icu, Ics, Icw, trip unit, spring charging, interlocking, and primary/secondary injection tests?

Primary vs secondary injection testing

Maintenance checks

  • Contact condition and contact resistance
  • Insulation
  • Trip unit
  • Closing and tripping coils
  • Spring mechanism
  • Auxiliary contacts
  • Interlocks
  • Terminal torque
  • Protection settings

Icu

Rated ultimate short-circuit breaking capacity (IEC 60947-2).

Ics

Rated service short-circuit breaking capacity, expressed as a percentage of Icu (25/50/75/100%); after an Ics interruption the breaker must remain fit for service.

Icw

Rated short-time withstand current for a stated duration (e.g. 1 s) — key for selectivity using short-time delay.

Trip unit

Electronic unit that senses current through CTs/sensors and commands the breaker to trip.

Spring charging

Stores mechanical energy for closing (and enables a fast open–close–open sequence).

Interlocking

Prevents unsafe operations — e.g. racking while closed, or closing two incomers in parallel.

Primary injection

Injects high current through the main primary circuit to test the whole chain: sensors, trip unit and mechanism.

Secondary injection

Injects test signals into the trip unit/relay sensing circuit to test settings and logic without high primary current.

Model interview answer

“For ACB maintenance I inspect the mechanism, contacts, arc chutes, terminals, spring charging system, trip and closing coils and the electronic trip unit. I perform contact resistance, insulation and protection tests as applicable. Primary injection verifies the complete protection path, while secondary injection is useful for testing trip-unit settings and logic.”

These answers summarise common industrial practice for interview preparation. Test voltages, acceptance limits, protection settings and statutory requirements vary by equipment, manufacturer and country — always follow the OEM documentation, applicable standards and your site's safety procedures.

FAQ

Frequently Asked Questions

What is the difference between an AVR and a governor on a DG set? +

The AVR controls alternator excitation and therefore output voltage and reactive power sharing. The governor controls engine fuel and therefore speed, which sets frequency and real power sharing. Voltage problems point to the AVR/excitation system, while frequency problems point to the governor, fuel system or load changes.

Why is 11 kV used instead of 10 kV? +

The classic explanation is that about 10% extra voltage is sent to cover the voltage drop along the line, so a nominal 10 kV at the receiving end is sent at 11 kV; the same pattern gives 22, 33, 66, 132 and 220 kV. It is not linked to the 1.11 form factor of a sine wave, and it does not apply to EHV levels such as 400 kV or 765 kV, which use reactive compensation instead. These levels are standard in India, the UK and many other networks, while other regions use values such as 10 kV or 20 kV in parts of Europe and 13.8 kV in North America.

What is the difference between MTBF and MTTR? +

MTBF (mean time between failures) is total operating time divided by the number of failures and reflects reliability. MTTR (mean time to repair) is total repair time divided by the number of repairs and reflects maintainability. Inherent availability can be estimated as MTBF divided by the sum of MTBF and MTTR.

What is the difference between an online and an offline UPS? +

An online (double-conversion) UPS feeds the load through its inverter all the time, so there is no transfer when the mains fails and the output is continuously conditioned. An offline (standby) UPS feeds the load from the mains and switches to its inverter only when the mains fails, with a short transfer time. Online UPS systems are preferred for PLCs, servers and instrumentation.

Why must boiler interlocks never be bypassed? +

Boiler interlocks and trips stop the burner or the boiler when a dangerous condition exists, such as low drum level, flame failure, incomplete purge or loss of a draft fan. Bypassing one can allow a furnace explosion or low-water damage. The correct approach is to trace the missing permissive through the sensor, wiring, PLC logic and actuator and fix the actual cause.

More Electrical Interview Questions

This is Part III of a three-part, 120-question series. Every question below opens directly on its own page.

Part I: Fundamentals, Motors & Protection

Questions 1–40

Electrical Fundamentals

Motors & Motor Maintenance

Protection & Switchgear

Open Part I →

Part II: Transformers, Cables, Testing & Instrumentation

Questions 41–80

Transformer & Power Distribution

Panels, Cables & Earthing

Electrical Testing & Troubleshooting

Electronics & Instrumentation

Open Part II →

Popular Maintenance Guides

Explore More Categories